Chapter 11 Project Communication Management Unit Test 11

1、 问题:( )used for large complex information sets, or for large audiences.
选项:
A:Interactive communication
B:Pull communication
C:Interpersonal communication
D:Push communication.
答案: 【Pull communication

2、 问题:( ) perform a multidirectional exchange of information between two or more parties.
选项:
A:Interactive communication
B:Push communication
C:Pull communication
D:Public communication.
答案: 【Interactive communication

3、 问题:Which of the following statements about Manage Communications is false?( )
选项:
A:Manage Communications is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information.
B:This process enables an efficient information flow between the project team.
C:This process does not need to be performed throughout the process.
D:The Manage Communications process identifies all aspects of effective communication.
答案: 【This process does not need to be performed throughout the process.

4、 问题:The mechanisms by which information is exchanged can be in:( )
选项:
A:Written form
B:Spoken form
C:Through gestures
D:Choice of words.
答案: 【Written form ;
Spoken form;
Through gestures;
Choice of words.

5、 问题:Factors that can affect the choice of communication technology include( )
选项:
A:Urgency of the need for information
B:Availability and reliability of technology
C:Ease of use
D:Project environment
答案: 【Urgency of the need for information;
Availability and reliability of technology;
Ease of use;
Project environment

6、 问题:Communication models can represent the communication process in its most basic linear.
选项:
A:正确
B:错误
答案: 【正确

7、 问题:Work performance data contains data on the types and quantities of communications that have actually been distributed.
选项:
A:正确
B:错误
答案: 【正确

Chapter 10 Project Quality Management Unit Test 10

1、 问题:( )occurring prior to delivery / shipment of the product or service, to the customer.
选项:
A:Internal failure costs
B:Prevention Costs
C:Appraisal Costs
D:External Failure Costs
答案: 【Internal failure costs

2、 问题:( ) conform with the cost of conformance.
选项:
A:Internal failure costs and Prevention Costs
B:Internal failure costs and External Failure Costs
C:Appraisal Costs and Prevention Costs
D:Prevention Costs and External Failure Costs
答案: 【Appraisal Costs and Prevention Costs

3、 问题:The most common quality management tool exclude ( )
选项:
A:The flow chart
B:Affinity diagrams
C:Cause-and-Effect Diagram
D:Mind mapping.
答案: 【Mind mapping.

4、 问题:( ) are the most common quality improvement tools.
选项:
A:Affinity diagrams
B:Plan-do-check-act
C:Six Sigma
D:Cause-and-Effect Diagram
答案: 【Plan-do-check-act;
Six Sigma

5、 问题:Plan-do-check-act cycle is the basis for quality improvement.
选项:
A:正确
B:错误
答案: 【正确

6、 问题:The cost of preventing mistakes is generally much higher than the cost of correcting them when are found by inspection.
选项:
A:正确
B:错误
答案: 【错误

Chapter 13 Project Resource Management Unit Test 13

1、 问题:Hierarchical charts exclude ( )
选项:
A:Work breakdown structures
B:Resource breakdown structure
C:Assignment Matrix
D:Organizational breakdown structure
答案: 【Assignment Matrix

2、 问题:The tools of estimate activity resources exclude ( )
选项:
A:Analogous estimating
B:Parametric estimating
C:Bottom-up estimating
D:Interval estimating
答案: 【Interval estimating

3、 问题:Resource categories in the resource breakdown structure include ( )
选项:
A:Labor
B:Material
C:Equipment
D:Supplies
答案: 【Labor;
Material;
Equipment;
Supplies

4、 问题:How do we measure performance? ( )
选项:
A:Observation
B:Information collection
C:Comparison between planned deliverables and current situation
D:Reporting
答案: 【Observation;
Information collection;
Comparison between planned deliverables and current situation;
Reporting

5、 问题:The key benefit of the Estimate Activity Resources is that it identifies the ( ) of resources required to complete the project.
选项:
A:Type
B:Quantity
C:Quality
D:Characteristics
答案: 【Type;
Quantity;
Characteristics

6、 问题:Planning for physical and human resources is much less predictable in projects with high variability.
选项:
A:正确
B:错误
答案: 【正确

7、 问题:Project resources can only be obtained from outside the organization through a procurement process.
选项:
A:正确
B:错误
答案: 【错误

Chapter 3 Project Management Body of Knowledge Unit Test 3

1、 问题:( )is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.
选项:
A:Direct and Manage Project Work
B:Develop Project Management Plan
C:Monitor and Control Project Work
D:Perform Integrated Change Control
答案: 【Develop Project Management Plan

2、 问题:A project may be managed in ( ) separate scenarios:
选项:
A:Two
B:Three
C:Four